UCDSB summer construction projects strengthen long-term infrastructure planning ahead of students’ return
- Tanya Hammond | Local Journalism Initiative Reporter | Review-Mirror
- 2 days ago
- 2 min read

As students across the Upper Canada District School Board (UCDSB) prepare to return to class this September, dozens of school construction and maintenance projects have been quietly transforming learning environments behind the scenes.
According to April Scott-Clarke, UCDSB manager of communications, these “school infrastructure projects are part of the long-term planning of our school district. We want to ensure our schools remain safe, sustainable, and meet the needs of our growing and changing communities.”
Many of the projects completed over the summer focused on essential systems such as HVAC upgrades, fire alarms and smoke detectors. While some improvements, like new air conditioning, will be immediately noticeable to students and staff, others are more subtle. “Generally, when these systems are being updated, they are nearing the end of their lifecycle, not when something is completely broken, so that there is no major disruption to the learning environment,” Scott-Clarke said.
One of the more visible projects this summer is the redesign of the bus lane and parking areas at Lombardy Public School. The goal is to improve daily traffic flow and enhance safety during peak times. Scott-Clarke noted that “this will lead to less congestion during the morning and afternoon drop-off and pick-up times, as well as improved overall site safety.”
With several schools across a large geographic region, deciding which buildings receive upgrades each summer is complex. The UCDSB relies on a long-term planning database maintained with the Ministry of Education, which tracks facility condition, equipment and site assets, says Scott-Clarke, noting that many factors come into play, including the age of the building and financial resources.
Summer construction in schools comes with a narrow window, often less than eight weeks; thus, to meet September deadlines, the UCDSB’s project management team works closely with contractors to keep projects on schedule. “Critical items are identified early in the project, and key dates are tracked with contingencies implemented as required,” Scott-Clarke explained.
In some cases, such as locally, Lombardy Public School’s HVAC system upgrade; Pineview Public School’s new fire alarm system installation and roof deck panel replacement; and South Crosby Public School’s fire alarm system upgrade and a new septic system installation, work may extend into the school year with contractors working after school hours to ensure a thorough completion of the projects.
While families may notice fresh pavement or new classroom cooling systems, much of the construction, like plumbing, electrical and fire alarm installation work, remains behind the walls. These upgrades are essential to maintaining safe, modern learning environments but rarely draw public attention.
Ultimately, each summer project contributes to a broader vision for the district’s future. By maintaining aging buildings, improving safety systems and modernizing learning environments, the UCDSB aims to keep its schools safe and comfortable for decades to come — a long-term infrastructure strategy that keeps students at the centre of every decision.